to complete a task in 16 days a company needs
5 people each working for 6 hours per day.
the company decides to have
8 people each working for 4 hours per day.
assuming that each person works at the same rate,
how many days will the task take to complete?

Respuesta :

Otras preguntas

What occurs during market equilibrium?
What is the 4th term of the geometric sequence with a=5 and ratio=3
a reflective essay most likely includes
What is the value of a
How does a cell move a molecule that is too large for transport proteins?
Many teens suffer from mental disorders. Today there are a number of treatment options available to these teens. Imagine that one of your friends is taking medi
What is one step you can take when using the strategy of looping? a. you freewrite about the subjects you have chosen. b. you identify your purpose of persuad
éclair croissant soufflé mousse au chocolat
What is the connection of citizenship and the right to vote?
how long has the googenheim been erected in new York city for?