The graphic shows the schedule network diagram (in minutes) for assembling a toy train set. What is the duration of the critical path?

A) 38 minutes
B) 41 minutes
C) 49 minutes
D) 51 minutes

The graphic shows the schedule network diagram in minutes for assembling a toy train set What is the duration of the critical path A 38 minutes B 41 minutes C 4 class=

Respuesta :

chocolateandchildren chocolateandchildren
  • 26-12-2018
D because it is longer than the rest
Answer Link

Otras preguntas

The biomedical revolution of the twentieth century caused population growth because _____.
What was the purpose of the Wilmot Proviso
What is it called when a writer uses figurative language that exaggerates a situation or characteristic
If the diploid number of chromosomes for an organism is twenty-six, what is the haploid number?
6th grade social studies
How do greenhouse gases affect visible and infrared light?
What is 1.2 liters - 200 milliliters
Somebody please help me I am leaving at 5:00
Last week, Brianna earned $565.75, which included a $100 bonus. She makes $11.50 an hour. Which equation and solution can be used to show how many hours Briann
In triangle XYZ, the length of side XY is 26 mm and the length of side YZ is 37 mm. Which of the following could be the length of side XZ?