In a work breakdown structure, the sequence of tasks in which there is no slack is referred to as:

Respuesta :

Kalahira
Kalahira Kalahira
  • 25-10-2017
Critical path, the sequence of the tasks where there is no slack. Meaning if one task doesn't start on time because another has not yet been completed, there is no down time and there will inevitably be a delay in the project.
Answer Link

Otras preguntas

______ is a generalization of the law of conservation of energy?​
A laptop computer is purchased for $1350. After each year, the resale value decreases by 35%. What will the resale be after 3 years.
what is the answer to this​
What does this sign mean?
Which ones correct I’ve taken this 3 times and I really don’t want to get it wrong again
Suppose 20% of all widgets produced at a factory are defective. A simulation is used to model widgets randomly selected and then recorded as defective or worki
write a letter to a newspaper explaining why you think the invention of ballpoint pen is very important ​
URGENT!!! What selection tool can you use as a round or circle selection tool by pressing the shift key? You can use the BLANK selection tool as a round or circ
The federal reserve's target rate for the federal funds rate is an extra policy tool for the central bank, in addition to and independent of the money supply. c
I need help with my music worksheet