If it takes 3 days for 10 workers to finish building one house, how many days will it take 15 workers to finish 4 houses?

Respuesta :

sirinda
sirinda sirinda
  • 19-10-2017
a = house
3 days x 10 worker = a
a = 30 work unit
4a = 120 work unit
120 work unit = 15 workers * y days
y = 120/15 = 8 days

i hope this isn't too confusing 
Answer Link

Otras preguntas

Tell the story of the predator/prey loop. If the owl population goes up, then ...
Suppose you've just heard an opera singer warm up her voice. Write your own science question about the sounds a singer makes.
The area of a square is 676 square feet. what is the perimeter of the square?
Write the slope intercept for of the equation of the line through the given points. (4, 2) and (0, -5). A) y=-7/4x-5 B) y=-5/4x-5 C) y=7/4x-5 D) y=5/4x-5
Which of the following is filling the role of a consumer?
HELP PLEASE ASAP Sara says, "If you subtract 13 from my number and multiply the difference by -6, the result is - 66." What is Sara's number?
detailed description of how group 1 atoms bond with group 7 atoms​
What are the recent cases which appears to have narrowed the scope of Miranda?
x-10<-26 help lololololol
-3x-2=13 please show steps on how to do